Sir Frank Markham School, Milton Keynes (Case Study No.1)

When the time came to build a new six classroom block (with toilet facilities), the MRC option offered a more cost effective answer than traditional construction.

This unit was manufactured in our factory over a two-week period and then erected on site, made watertight, equipped and ready for use in just two and a half weeks from delivery. In fact, the entire project, from laying concrete foundations to fitting the carpets, took just six weeks.

The walls were pre-finished with vinyl on plasterboard, meaning that there were no ‘wet trades’ on site, which helped speed-up the assembly of the unit considerably. Each module came with doors and double-glazed windows, internal partitioning and lighting ready for use. The thermal insulation and advanced heating and ventilation systems comply fully with current Building Regulations – exactly the same regulations as a traditionally built construction.

All works were carried out by MRC’s own operatives, using our own plant and equipment, and without involving subcontractors.

The result was completion right on schedule – enabling the students to start the new term in style.

Norwich City Football Club (Case Study No. 2)

While year-long upgrading work to its existing facilities was in progress, the club required a high specification changing facility – four changing rooms with showers and toilets in a high performance Plastisol finish.

This unit was manufactured in our factory over a two-week period, with one week to install the unit and prepare it for use, and a further three weeks on site for all the completion works. Extra time was taken to install specialised heat-controlled shower units to our client’s high specification. This project was designed by us in collaboration with the football club to ensure their satisfaction.

From start date to possession, then, the work was completed in just eight weeks – another successful project carried out by MRC and its workforce.

Derbyshire County Council, William Allitt School, Swadlincote (Case Study No. 3)

A four-classroom music suite with toilet facilities, to include an additional tarmac parking area, and concrete and brick ramps for disabled access – this was the County Council’s demanding brief, made even more demanding by the requirement for completion within eight weeks.

To enable the school to use the music suite whilst the above installation was taking place, we also provided a further four classroom unit on a temporary hire basis – both projects conforming to all relevant building control requirements and providing specialist sound-proofing and wall boarding.

The speed and flexibility of the MRC system enabled us to complete the project on time and to our clients’ satisfaction.